#TeamFCEO is pleased to announce the completion of the Reese Road 0.23 over Big Walnut Creek Improvement Project. We extend our gratitude to Complete General Construction Company and our project partners for their dedicated efforts and commitment to completing the project ahead of schedule.
Franklin County Engineer
Franklin County Engineer
Reese Road, between Bixby Road and Rathmell Road is now opened to traffic.
Franklin County Engineer
Franklin County Engineer
Ferris Road, between Cleveland Avenue and Westerville Road, is now opened to traffic.
Franklin County Engineer
Franklin County Engineer
As roundabouts increase throughout Franklin County, it's key to know the rules! Always remember to slow down, stay alert, and be ready to yield. Watch this quick guide to mastering roundabout etiquette: https://www.youtube.com/watch?v=pTzWibBhSwg.
Franklin County Engineer
Franklin County Engineer
Ferris Road, between Cleveland Avenue and Westerville Road, is closed due to downed power lines as a result of a vehicle crash. The road will remain closed until the issue has been resolved.
Franklin County Engineer
Franklin County Engineer
Sandusky Street, south of Alkire Road, will be closed beginning Monday, September 23, 2024, for a railroad crossing repair. The closure will last approximately three (3) days, weather permitting.
Franklin County Engineer's Office
970 DUBLIN ROAD
COLUMBUS, OHIO 43215
(614) 525-3030
fracoeng@franklincountyengineer.org
Top
 

2015 Construction Projects

2015 Construction Projects

The following projects were completed during the 2015 construction season:

Dublin Road and Fishinger Road

Location: The intersection of Dublin Road and Fishinger Road
Description: Widening both Dublin Road and Fishinger Road to improve right turn lanes
Status: The project is complete.
Contractor: Strawser Paving Co., Inc

Alkire Road and Demorest Road

Location: The intersection of Alkire Road and Demorest Road
Description: Construction of a single lane modern roundabout.
Status: The project is complete.
Contractor: Strawser Paving Co., Inc

Chatterton Road at Fontaine Road and Reynard Road

Location: Chatterton Road, Fontaine Road and Reynard Road intersection.
Description: Improvement of Chatterton Road by widening the pavement to provide a center turn lane between Fontaine Road and Reynard Road
Status: The project is complete.
Contractor: Strawser Paving Co., Inc

Snouffer Road Pedestrian Crossing

Location: At the intersection of Snouffer Road and Snouffer Place-Bride Water Boulevard.
Description: Installment of a pedestrian crossing, which will include a rectangular rapid flashing beacon
Status: The project is complete.
Contractor: Columbus Asphalt Paving, Inc

Zuber Road over Frederick-Francis Ditch

Location: Between Ridpath Road and Hoover Road
Description: Replacement of an existing reinforced concrete box culvert over Frederick-Francis Ditch with a precast concrete box culvert and approach work.
Status: The project is complete.
Contractor: Buds, Inc.