Franklin County Engineer Facebook Feed

Franklin County Engineer

As a local public works agency headquartered in Columbus, Ohio, the Franklin County Engineer's Office is responsible for the maintenance and construction of 271 miles of county roadway and 351 county bridges, as well as upkeep of all county ditches, drains, retention basins, and other storm water facilities within the right-of-way of county roads in unincorporated areas. To meet the continuing development and infrastructure needs of Franklin County, the Engineer's Office utilizes the latest technologies for determining and maintaining roadway centerlines and boundaries; retracing and setting new monuments for original public land surveys; preparing geographic information system mapping for real estate tax assessments; and establishing precise countywide horizontal and vertical control to maintain uniformity in construction, surveying, and mapping.
Franklin County Engineer
Franklin County Engineer
Our offices are closed today in recognition of Thanksgiving. We will reopen Friday, November 27, 2020 at 7:00 am. Please be safe everyone!
Franklin County Engineer
Franklin County Engineer
Meet Raelynn McCown! She's been with FCEO for a year and works in our Planning and Programming Dept. In her spare time, Rae enjoys being outdoors, repurposing/building home furniture, and spending time with family and friends. Thanks Rae for being #TeamFCEO! #WorkerWednesday
Franklin County Engineer
Franklin County Engineer
The positivity rate in our community is high. The incubation period for COVID-19 is 2-14 days. You can unknowingly spread if you have been exposed, even if you have a negative test.

We all need to stay home as much as possible and not gather. We understand this is difficult but it is in the best interest of our community and the health of each of us. Columbus - we need to work together to slow the spread!
Franklin County Engineer
Franklin County Engineer
#TeamFCEO hosted the 2021 Construction Project List Virtual Open House. We provided a preview of our upcoming construction projects and afterwards held a Q&A session. Thank you to everyone who joined us! Visit http://www.franklincountyengineer.org/future-projects/ to view the presentation.
Franklin County Engineer
Franklin County Engineer
The intersection of Alkire Road and Galloway Road is now open to traffic.
Franklin County Engineer
Franklin County Engineer
Thanksgiving is almost here! So make sure you know the best ways to stay safe.

Tip #1: Very familiar faces only! This year the stuffing should be passed to people who live in your household.

For more info on Thanksgiving safety, go here: https://bit.ly/3nNHudn

Franklin County Engineer's Office
970 DUBLIN ROAD
COLUMBUS, OHIO 43215
(614) 525-3030
fracoeng@franklincountyengineer.org
Top
 

Current Construction Projects

Current Construction Projects

Location: Mann Road between Havens Road and Havens Corners Road

Description: Replace Concrete Slab Culvert

Status: September 8, 2020 for approximately 45 Days, weather permitting

Traffic/Detours: The posted detour route for southbound motorists will follow Clark State Road, west to Hamilton Road, south to Havens Corners Road, and east to Mann Road. Northbound motorists will follow the detour in the opposite direction.

Work Provider: Axis Civil Construction LLC.

Road Construction Bulletin

Location: The Intersection of Reynoldsburg-New Albany Road and Clark State Road to be Closed for Roundabout Construction

Description: Construction of a New Modern Roundabout

Status: August 3, 2020, for approximately 75 Days, weather permitting

Traffic/Detours: See the attached drawing for detour details

Work Provider: Double Z Construction Co.

Road Construction Bulletin

Location: Ridpath Road 0.65 Miles south of Zuber Road

Description: Bridge Replacement

Status: July 13, 2020 for 45 days, weather permitting

Traffic/Detours: The posted detour route for southbound motorists will follow Zuber Road, east to Hoover Road / Welch Road, south to Snyder Road, and west to Ridpath Road. Northbound motorists will follow the detour route in the opposite direction.

Work Provider: Darby Creek Excavating, Inc

Road Construction Bulletin

Location: Dublin-Granville Road between Hamilton Road and Harlem Road

Description: Bridge Replacement

Status: July 13, 2020 for 120 days, weather permitting

Traffic/Detours: The posted detour route for motorists traveling east on Dublin-Granville Road will follow Hamilton Road north to SR 161, east to New Albany Road, south to Fodor Road, and south to Dublin-Granville Road. Westbound motorists will follow the detour route in the opposite direction.

Work Provider: Shelly & Sands, Inc.

Road Construction Bulletin

Location: Borror Road and Buckeye Parkway

Description: Construction of a single lane modern roundabout.

Status: June 22, 2020 for 45 Days, weather permitting.

Traffic/Detours: See the attached image for detour information.

Work Provider: Complete General Construction Co.

Road Construction Bulletin

Location: Hayden Run Road under I-270

Description: Shared use path construction

Status: Under construction, to be completed in September, weather permitting.

Traffic/Detours: A 15-day closure will occur in late June or early July

Work Provider: Double Z Construction

Location: Intersection of Alum Creek Drive and Rohr Road

Description: Intersection improvement

Status: Under construction, to be completed in the spring of 2020

Traffic/Detours: Traffic will be maintained

Work Provider: Shelly & Sands

Location: Waggoner Road between Havens Road and Havens Corners Road

Description: Road Widening and Box Culvert Replacement

Status: April 27, 2020  for 45 days, weather permitting

Traffic/Detours: The posted detour route for southbound motorists on Waggoner Road will follow Clark State Road west to Reynoldsburg-New Albany Road, south to Havens Corners Road, and east to Waggoner Road. Northbound motorists will follow the detour route in the opposite direction.

Work Provider: SAVKO Construction Company

Road Construction Bulletin

Location: Alum Creek Drive

Description: Mobility Improvement

Status: April 6, 2020 until early Fall, weather permitting.

Traffic/Detours: Northbound and/or southbound lanes will close periodically at night as project progresses.

Work Provider: Gudenkauf Corporation

Plan Title Sheet

Location: Havenwood Area including Lincoln Park Court, Nationwide Boulevard and Westport Road

Description: Roadway and Sidewalk Rehabilitation

Status: March 16, 2020 for 90 days, weather permitting.

Traffic/Detours: Access to all Residents will be maintained with a One Way Traffic Pattern. Traffic will switch sides of the road as the project progresses and will be signed accordingly.

Work Provider: Strawser Paving Company

Road Construction Bulletin

Location: Trabue Road Bridge over Norfolk Southern Railroad, between Walcutt Road and Westbelt Drive

Description: Bridge Structure Rehabilitation and Addition of a Shared Use Path

Status: March 9, 2020 for 150 days, weather permitting.

Traffic/Detours: The posted detour route for eastbound motorists will follow Walcutt Road north to Roberts Road, east to Westbelt Drive, and south to Trabue Road. Westbound motorists will follow the detour route in the opposite direction.

Work Provider: Complete General Construction Company

Road Construction Bulletin