Description:
Widening and resurfacing of Alum Creek Drive, including the I-270 Ramp.
Improvements involve the construction of new asphalt pavement, storm sewers, shoulders, curbing, and
guardrail; and the widening of the roadway, at Groveport Road, to accommodate
the addition of through, left, and right turn lanes on both sides of Alum Creek
Drive.
This work is in preparation for
the future reconstruction and realignment of Groveport Road.
Status:
The project is scheduled to start in August 2010.
Traffic:
Traffic will be maintained during construction. Motorists should expect slower
than normal travel and possible delays.
Contractor:
To be determined.
Cost:
Estimated at $4 million to be funded by the
Ohio Department of Development, Federal
Highway Administration, through the Mid-Ohio
Regional Planning Commission, and private sector contributions.